SOCIOECONOMIC IMPACT MITIGATION

STANDARD OF REVIEW

The Mitigation Agreement is described in the CBJ Mining Ordinance at 49.65.135(a)(7) which states that the operator will negotiate and enter into an agreement with CBJ to establish responsibility for the mitigation of reasonably foreseeable and demonstrable adverse impacts. The operator is responsible for direct impacts. The CBJ is responsible for mitigating indirect impacts except where the costs of so doing are found by the City Manager to:

A. exceed the amount of any CBJ nonproprietary revenue increase attributable to the mining operation, and

B. require a direct and significant increase in local taxes or fees to adequately mitigate the impact.

If this fiscal condition were to occur, then the CBJ would seek mitigation for indirect impacts from the operator.

Further, the Mining Ordinance (CBJ 49.65.130(c)) requires that a Socioeconomic Impact Assessment (SIA) be prepared to provide information on beneficial and adverse impacts of the mining operation on existing and future local conditions and on the CBJ fiscal condition and general government functions. The SIA provides information in order that the CBJ determine the extent of these impacts and how they can be mitigated.

Highly speculative impacts are not included in the SIA or as part of the Mitigation Agreement. The Agreement is to be incorporated as part of the large mine permit.

BACKGROUND

A Draft Socioeconomic Impact Assessment (SIA) was prepared for the CBJ by Reed Hansen and Associates and released for public review in February 1997. A public hearing was held by the Planning Commission on March 4, 1997. The Final SIA was issued in May 1997.

The goal of the SIA is to estimate reasonably foreseeable and demonstrable impacts of the Kensington mine project on the following selected issues of importance to the CBJ:


The study of the Kensington mine-induced impacts was approached as a "marginal impact analysis". The impacts of the project are predicted by analyzing the above-mentioned issues for the Juneau community both with and without the Kensington mine. The study develop two scenarios, or predictions for the future. These predictions are known as the "baseline" (without the project) and the "with project" scenarios. For any particular issue, the difference between the two is the impact of the mine project.

The SIA is based on extensive data-gathering and numerical modeling -- similar to the study performed in 1991-92 for the earlier Kensington mine proposal. The SIA is considerably more detailed than analyses for other purposes, such as an environmental impact statement, in order to develop a greater level of accuracy and information about the net impacts of the project. The analysis provides the basis for a mitigation agreement between the mine operator and the CBJ.

In summary, the SIA predicts the following socioeconomic impacts of the Kensington mine project:

ANALYSIS

According to the Kensington Socioeconomic Impact Assessment projections, the non-proprietary revenues to CBJ as a result of the Kensington mine project will exceed the projected CBJ expenditures for mine-induced indirect impacts to the community over the life of the project. The Kensington mine would not provide proprietary revenues to CBJ, such as royalties from ownership of the subsurface mineral rights. Thus, CBJ anticipates at this time that the local government will be responsible for mitigating indirect socioeconomic impacts from mine-related revenues.

Chapter VII of the Final SIA provides some suggestions for mitigating certain impacts anticipated from population growth induced by the Kensington mine. The areas of impacts identified for which mitigation may be needed are school enrollment/capacity, housing, day care facilities, chemical dependency/mental health services, and early mine closure.


At this time, CBJ and Coeur have negotiated a Socioeconomic Impact Mitigation Agreement. In general terms, the attached draft Mitigation Agreement:

1. defines the mine-related responsibilities of each party with respect to direct and indirect impacts;

2. provides for adjustments or amendments to the Agreement in the event that actual population-induced costs and non-proprietary revenues related to the mine are different than projected;

3. identifies socioeconomic factors (such as workforce size and demographics, assessed mine valuation and tax rates) that will be monitored during the life of the mine project;

4. provides for enforcement and assignment of the mitigation agreement; and

5. identifies Coeur Alaska, Inc. as the mine operator and responsible for the provisions of the Agreement.

Upon request, the City and Borough Manager allowed counsel for the Kensington Coalition to participate in the recent Mitigation Agreement negotiations between the CBJ and Coeur. At Coeur's request, the CBJ agreed to include a provision in the draft Mitigation Agreement (paragraph 2.2.2) that addresses socioeconomic mitigation measures regarding housing, child care, and school construction. The CBJ makes a commitment that, at such time when Coeur and the Kensington Coalition ratify their separate settlement agreement, the CBJ will renegotiate the Mitigation Agreement with Coeur to achieve the purposes of the housing, child care, and school construction provisions in the settlement agreement. In effect, Coeur would be committing to provide housing, child care services for its employees, and a proportionate share of the costs to construct a new school. The CBJ would enforce such provisions in a renegotiated Mitigation Agreement. While recognizing that under the anticipated costs and revenues in the Final SIA the CBJ has no authority to require Coeur to mitigate indirect impacts, the CBJ nevertheless agrees to this provision in support of efforts by Coeur and the Kensington Coalition to avoid litigation.

STAFF FINDINGS

1. Was a socioeconomic impact assessment prepared in accordance with the Mining Ordinance? CBJ 49.65.130(c)(1)

Yes. An SIA was prepared by an independent consultant retained by the Community Development Department. A draft SIA was distributed in February 1997. A public hearing on the draft was conducted on March 4, 1997. The final SIA was released in May 1997.

2. Has the operator negotiated and entered into a Mitigation Agreement?

CBJ 65.135(a)(7))

The operator has negotiated with the City and Borough Manager to establish a Mitigation Agreement. The parties have tentatively agreed to the provisions contained in the attached draft Mitigation Agreement. The City and Borough Manager provided the draft Agreement to the Planning Commission for its review and comment at its September 24, 1997 special meeting. The Agreement would be incorporated into the large mine permit, and the operator would enter into the Agreement by signing before CBJ issues any permit for the Kensington mine project.

As part of the attached draft Agreement, the City and Borough Manager finds that the costs of mitigating reasonably foreseeable and demonstrable indirect impacts of the mining operation do not exceed the amount of CBJ non-proprietary revenue increase attributable to the mining operation, based on the estimates in the Final SIA. Further, the Final SIA does not suggest, nor the Manager find, the need for a significant tax increase to mitigate anticipated indirect impacts. Therefore, the CBJ will be responsible for mitigating indirect impacts of the project, in accordance with the government services and facilities CBJ typically provides to local residents. Staff finds that the Final SIA adequately anticipates the provision of these routine government services and facilities as a function of mine-induced population growth and its effect on the CBJ fiscal expenditures during the life of the mine.

As part of the attached draft Agreement, Coeur agrees to comply with all conditions imposed upon it by the large mine permit. Staff finds that the safeguards, practices, and monitoring of the proposed project, together with the conditions of the large mine permit, will mitigate the direct impacts of the project.

STAFF RECOMMENDATION

Staff recommends that the draft Socioeconomic Impact Mitigation Agreement negotiated by the City and Borough Manager be incorporated into the large mine permit.


Return to Kensington Mine Review Page
Return to the Capital City Home Page

Our URL is http://www.juneau.lib.ak.us/cdd/Kensingt.htm

Last revised on 06/28/99 - bgb