SOCIOECONOMIC IMPACT MITIGATION
STANDARD OF REVIEW
The Mitigation Agreement is described in the CBJ Mining
Ordinance at 49.65.135(a)(7) which states that the operator will
negotiate and enter into an agreement with CBJ to establish
responsibility for the mitigation of reasonably foreseeable and
demonstrable adverse impacts. The operator is responsible for
direct impacts. The CBJ is responsible for mitigating indirect
impacts except where the costs of so doing are found by the City
Manager to:
A. exceed the amount of any CBJ nonproprietary revenue
increase attributable to the mining operation, and
B. require a direct and significant increase in local taxes or
fees to adequately mitigate the impact.
If this fiscal condition were to occur, then the CBJ would
seek mitigation for indirect impacts from the operator.
Further, the Mining Ordinance (CBJ 49.65.130(c)) requires that
a Socioeconomic Impact Assessment (SIA) be prepared to provide
information on beneficial and adverse impacts of the mining
operation on existing and future local conditions and on the CBJ
fiscal condition and general government functions. The SIA
provides information in order that the CBJ determine the extent
of these impacts and how they can be mitigated.
Highly speculative impacts are not included in the SIA or as
part of the Mitigation Agreement. The Agreement is to be
incorporated as part of the large mine permit.
BACKGROUND
A Draft Socioeconomic Impact Assessment (SIA) was
prepared for the CBJ by Reed Hansen and Associates and released
for public review in February 1997. A public hearing was held by
the Planning Commission on March 4, 1997. The Final SIA was
issued in May 1997.
The goal of the SIA is to estimate reasonably foreseeable and
demonstrable impacts of the Kensington mine project on the
following selected issues of importance to the CBJ:
The study of the Kensington mine-induced impacts was
approached as a "marginal impact analysis". The impacts
of the project are predicted by analyzing the above-mentioned
issues for the Juneau community both with and without
the Kensington mine. The study develop two scenarios, or
predictions for the future. These predictions are known as the
"baseline" (without the project) and the "with
project" scenarios. For any particular issue, the difference
between the two is the impact of the mine project.
The SIA is based on extensive data-gathering and numerical
modeling -- similar to the study performed in 1991-92 for the
earlier Kensington mine proposal. The SIA is considerably more
detailed than analyses for other purposes, such as an
environmental impact statement, in order to develop a greater
level of accuracy and information about the net impacts of the
project. The analysis provides the basis for a mitigation
agreement between the mine operator and the CBJ.
In summary, the SIA predicts the following socioeconomic
impacts of the Kensington mine project:
ANALYSIS
According to the Kensington Socioeconomic Impact Assessment
projections, the non-proprietary revenues to CBJ as a result of
the Kensington mine project will exceed the projected CBJ
expenditures for mine-induced indirect impacts to the community
over the life of the project. The Kensington mine would not
provide proprietary revenues to CBJ, such as royalties from
ownership of the subsurface mineral rights. Thus, CBJ anticipates
at this time that the local government will be responsible for
mitigating indirect socioeconomic impacts from mine-related
revenues.
Chapter VII of the Final SIA provides some suggestions
for mitigating certain impacts anticipated from population growth
induced by the Kensington mine. The areas of impacts identified
for which mitigation may be needed are school
enrollment/capacity, housing, day care facilities, chemical
dependency/mental health services, and early mine closure.
At this time, CBJ and Coeur have negotiated a Socioeconomic
Impact Mitigation Agreement. In general terms, the attached draft
Mitigation Agreement:
1. defines the mine-related responsibilities of each party
with respect to direct and indirect impacts;
2. provides for adjustments or amendments to the Agreement in
the event that actual population-induced costs and
non-proprietary revenues related to the mine are different than
projected;
3. identifies socioeconomic factors (such as workforce size
and demographics, assessed mine valuation and tax rates) that
will be monitored during the life of the mine project;
4. provides for enforcement and assignment of the mitigation
agreement; and
5. identifies Coeur Alaska, Inc. as the mine operator and
responsible for the provisions of the Agreement.
Upon request, the City and Borough Manager allowed counsel for
the Kensington Coalition to participate in the recent Mitigation
Agreement negotiations between the CBJ and Coeur. At Coeur's
request, the CBJ agreed to include a provision in the draft
Mitigation Agreement (paragraph 2.2.2) that addresses
socioeconomic mitigation measures regarding housing, child care,
and school construction. The CBJ makes a commitment that, at such
time when Coeur and the Kensington Coalition ratify their
separate settlement agreement, the CBJ will renegotiate the
Mitigation Agreement with Coeur to achieve the purposes of the
housing, child care, and school construction provisions in the
settlement agreement. In effect, Coeur would be committing to
provide housing, child care services for its employees, and a
proportionate share of the costs to construct a new school. The
CBJ would enforce such provisions in a renegotiated Mitigation
Agreement. While recognizing that under the anticipated costs and
revenues in the Final SIA the CBJ has no authority to require
Coeur to mitigate indirect impacts, the CBJ nevertheless agrees
to this provision in support of efforts by Coeur and the
Kensington Coalition to avoid litigation.
STAFF FINDINGS
1. Was a socioeconomic impact assessment prepared in
accordance with the Mining Ordinance? CBJ 49.65.130(c)(1)
Yes. An SIA was prepared by an independent consultant retained
by the Community Development Department. A draft SIA was
distributed in February 1997. A public hearing on the draft was
conducted on March 4, 1997. The final SIA was released in May
1997.
2. Has the operator negotiated and entered into a Mitigation Agreement?
CBJ 65.135(a)(7))
The operator has negotiated with the City and Borough Manager
to establish a Mitigation Agreement. The parties have tentatively
agreed to the provisions contained in the attached draft
Mitigation Agreement. The City and Borough Manager provided the
draft Agreement to the Planning Commission for its review and
comment at its September 24, 1997 special meeting. The Agreement
would be incorporated into the large mine permit, and the
operator would enter into the Agreement by signing before CBJ
issues any permit for the Kensington mine project.
As part of the attached draft Agreement, the City and Borough
Manager finds that the costs of mitigating reasonably foreseeable
and demonstrable indirect impacts of the mining operation do not
exceed the amount of CBJ non-proprietary revenue increase
attributable to the mining operation, based on the estimates in
the Final SIA. Further, the Final SIA does not suggest, nor the
Manager find, the need for a significant tax increase to mitigate
anticipated indirect impacts. Therefore, the CBJ will be
responsible for mitigating indirect impacts of the project, in
accordance with the government services and facilities CBJ
typically provides to local residents. Staff finds that the Final
SIA adequately anticipates the provision of these routine
government services and facilities as a function of mine-induced
population growth and its effect on the CBJ fiscal expenditures
during the life of the mine.
As part of the attached draft Agreement, Coeur agrees to
comply with all conditions imposed upon it by the large mine
permit. Staff finds that the safeguards, practices, and
monitoring of the proposed project, together with the conditions
of the large mine permit, will mitigate the direct impacts of the
project.
STAFF RECOMMENDATION
Staff recommends that the draft Socioeconomic Impact Mitigation Agreement negotiated by the City and Borough Manager be incorporated into the large mine permit.
Return
to Kensington Mine Review Page
Return to the
Capital City Home Page
Our URL is http://www.juneau.lib.ak.us/cdd/Kensingt.htm