RECLAMATION
STANDARD OF REVIEW
A reclamation plan is an essential feature of the overall
mining project plan and is a requirement of the CBJ Large Mine
Permit. According to the CBJ Mining Ordinance (49.65.135(a)), the
CBJ shall require that:
Also, CBJ 49.65.135(b) requires that:
Thus, the Mining Ordinance requires approval of a reclamation
plan, and specifies the requirements of that reclamation plan.
Also, the Mining Ordinance (CBJ 49.65.140 (a)) requires a
financial warranty to:
Finally, the Mining Ordinance (CBJ 49.65.145(d)) requires that
at the end of a temporary mine closure, or:
This staff report examines the Reclamation Plan for content
and approvability. In reviewing and evaluating the reclamation
plan submitted by the applicant, the CBJ staff applied the
following general criteria:
o There must be firm commitments to accomplish
reclamation in a timely manner.
o The reclamation strategy must be flexible and
adaptable to various stages of mine development.
o The proposed techniques must be of proven efficacy
in Southeast Alaska.
o The reclaimed site should be self-sustaining,
requiring little or no maintenance.
o The post-reclamation site must endure for centuries all reasonably anticipated natural disturbances free of adverse environmental impacts.
In addition to these general criteria, several specific
performance criteria were used:
o The mine tailings must be shielded from erosion by
water and wind.
o Mine openings must be sealed in the interests of
safety, but the mine must be allowed to drain freely as
long as it meets Alaska Water Quality Standards.
o Visual impacts of the mining activity, especially
facilities such as the dry tailings facility that are
visible from Lynn Canal, must be addressed during, as
well as after, mining operations.
o The facilities shall be designed such that 10 years after closure there will be either no need for further maintenance, or only a low level of maintenance that can be paid for reliably by a permanent funding source established for that purpose.
This staff report examines the proposed reclamation
activities, post-reclamation maintenance and monitoring,
financial warranty requirements and release criteria, and
administrative issues. The staff report on Visual Resources
recommends permit conditions that address interim and final
reclamation activities to minimize visual impacts of the project.
The staff report on Financial Warranty considers in detail the
specific costs of reclamation.
ANALYSIS
A Reclamation Plan was submitted for CBJ review in
January 1997 Following release of the Final SEIS, the applicant
revised the Reclamation Plan (August 1997) to correspond
with the preferred Alternative D. Discussions and correspondence
about the reclamation plan between the applicant, and
CBJ staff, and other agencies provided additional information
which is incorporated into the revised Reclamation Plan and this
staff analysis. The plan covers a broad range of topics including
interim and final reclamation, post reclamation maintenance,
warranty release criteria, and, to some extent, administrative
issues.
The Kensington mine is projected to disturb about 269 acres
(see attached Table 1.2; Reclamation Plan; August 1997).
The project changes resulting from preferred Alternative D in the
Final SEIS yield an additional 18 acres of surface disturbance,
primarily at the till borrow pit. The Reclamation plan also
describes the array of steps to be taken to reclaim the various
components of the mine site.
Interim Reclamation Issues
Two general categories of interim reclamation are described in
the plan: 1) concurrent reclamation that minimizes the
extent of site disturbance by continually reclaiming disturbed
sites as soon after the disturbance as practical, and 2) temporary
mine shut-down reclamation that keeps up routine erosion
control and prevention activities during a temporary cessation of
mine production.
Concurrent reclamation is featured in the routine development
and operation of the dry tailings facility (DTF) and the borrow
pits. This activity is similar to what is done in final
reclamation, consisting of grading, top soiling and seeding each
area of disturbed ground as soon as it is no longer required for
production purposes. For instance, borrow areas will be reclaimed
as soon as their gravel resources are exhausted, with regrading
occurring within one year of completed use and subsequent
revegetation. Individual DTF cells will be reclaimed as they
reach capacity. Initial revegetation will focus on grasses for
stabilization that then allows for succession of native plants,
alder, spruce, and hemlock. The applicant proposes to evaluate
the revegetation success -- particularly the regenerating
potential of native plant species -- during DTF concurrent
reclamation through the use of test plots. Modifications can be
made to the depth of growth media, plant species, seed mixtures,
soil amendments and fertilizer, based on test results and in
consultation with the regulatory agencies. Additional test plots
will evaluate revegetation strategies for other reclaimed habitat
types at the mine site.
The cost of performing concurrent reclamation is borne by the
operating budgets for gravel till extraction and tailings
disposal. One practical effect of concurrent reclamation is to
limit the amount of total site area in a disturbed and
unreclaimed state at any one time, thereby limiting the amount of
reclamation bonding that must be maintained.
The plan also anticipates interim reclamation measures that would be in effect up to three years in the event mining operations are suspended due to adverse economic conditions -- a common occurrence in the mining industry. It is seldom possible to forecast the duration of such a shut-down at the beginning. It could be a matter of a few weeks or months, or it could be many years (50-plus in the case of the AJ Mine) before mining resumes. Not knowing how long the period of inactivity will last makes it difficult to tailor interim reclamation measures to the occasion at hand.
The general approach proposed for reclamation during shut-down
periods is the same as the program of continuing maintenance
ongoing for the operating life of the mine. Activities such as
mothballing equipment and mounting a watchman operation may also
be involved, but otherwise the intent of the reclamation plan is
to maintain the site and facilities in the same fashion as during
normal mine operation. The main activities are keeping drainage
structures clear and inhibiting erosion of exposed soils with
annual seeding. Monitoring of air and water quality for
compliance with environmental requirements would continue.
Final Reclamation
According to the Reclamation Plan (August 1997),
interim reclamation activities would be limited in duration to a
maximum three-year production shutdown. Final reclamation would
begin at the end of such a shutdown unless the regulatory
agencies grant an extension. The goal of final reclamation is to
return all disturbed areas of the site to a stable and productive
condition. This includes minimizing visual impacts of the project
while protecting long-term land and water resources and
reestablishing, to the extent feasible, the wildland character of
the site. The Modified Landscape land use designation under the
revised Tongass Land and Resource Management Plan calls for
reclaiming the inland area of the major mine facilities such as
the borrow pits, process area, and DTF to achieve a Modification
visual quality objective (i.e., alterations visually dominate but
are compatible with natural surroundings). The shoreline would be
restored to a Partial Retention visual quality objective of
alterations which are visually subordinate to the natural
surroundings. See the staff report on Visual Resources for
further discussion of the visual quality objectives with
reclamation.
Specific reclamation tasks include facility shutdown and
decommissioning, demolition and removal of surface facilities,
portal closure, stream channel stabilization, fill placement and
grading, growth medium placement, revegetation and monitoring.
The plan deals with the removal of buildings and other surface
facilities including roads in a fairly straightforward fashion.
Superstructures and equipment will be removed from the site,
concrete foundations will be broken up and buried, and disturbed
areas will be regraded to enhance drainage and slope stability
and revegetated. Diverted streams will be returned to their
natural channels. According to the plan, only the existing camp
buildings, which are located on patented land near the beach,
will remain after mine closure.
The reclamation plan anticipates that land subsidence will not
reach the ground surface as the result of ore extraction under
the current mining plan. If this is the case, the amount of water
draining out of the mine should be modest, although at times
during the winter it may comprise the bulk of surface flows in
Sherman Creek. However, should subsidence occur, mine drainage
will become more problematical with implications for the portal
closure phase of reclamation. The staff report on Subsidence
discusses this contingency in some detail.
The revised Reclamation Plan (August 1997) identifies a series
of objectives to be achieved with reclamation, ranging from the
stabilization of steep slopes and protection of surficial soil
materials to establishment of self-sustaining vegetation and
pre-mining recreational uses. The plan also presents priorities
among the objectives for reclaiming specific project components,
based on agency and applicant discussions. This helps to clarify
the primary focus intended for particular reclamation activities,
now and in the future.
A major stated goal of the reclamation plan is to restore the
area to pre-mine wildlife habitat capability. This does not
necessarily mean that the area will be restored to the exact
pre-mine successional communities. The surface revegetation
strategy described in the reclamation plan would initially
establish grasses by hydroseeding. In this initial stage,
reclamation is focused on stabilization of slopes and devegetated
areas to allow for natural successional plant communities. As
noted earlier, throughout the life of the project, the applicant
will maintain test plots at the mine site. This will establish
the most appropriate vegetation mix to re-establish the different
habitat types in this area.
Viewed from Lynn Canal, the most visible aspect of the
Kensington mine would be the dry tailings facility, which, when
fully developed, will present a large smooth facade contrasting
sharply with the surrounding forest. As part of both concurrent
and final reclamation, the plan calls for continuously grading,
top soiling and revegetating the sloping sides of the dry
tailings facility as each cell is constructed. The overall intent
of this program is to reduce to a minimum (although it will not
eliminate) the visual contrast between the dry tailings facility
and the surrounding terrain.
The U.S. Forest Service, in the Final SEIS (1997) calls
for at least 1 foot depth in growth media at reclaimed sites and
identifies grass seeds for revegetation known to be successful in
Southeast Alaska. The Final SEIS also calls for 75 percent live
cover and meeting Alaska water quality standards as the set of
performance standards by which the success of the surface
restoration will be measured. These standards will become part of
the reclamation plan prior to U.S. Forest Service approval of the
final Plan of Operations Also, these standards can be used to
measure the operator's compliance as specified in CBJ Mining
Ordinance 49.65.135(b), and will serve as criteria for release of
a financial warranty for reclamation.
Wetland areas where borrows occur will be restored in terraces
to function as a combination of wet soils and open waters
throughout most of the year. The attached cross section (Figure
4-14; Section 404 permit application) shows a general contour for
one of these borrow areas.
During mine reclamation the three bridges placed across Upper Sherman and Ivanhoe Creeks will be removed and the areas disturbed by bridge abutments recontoured with the surrounding topography to blend with natural shapes. The Reclamation Plan then calls for rip rap along the stream channel segments for stabilization. A secondary reclamation objective identified in the Reclamation Plan is to protect surface water quality and reestablish fish habitat in these reclaimed areas.
As discussed by the agencies and applicant, staff believes
that some flexibility is needed in the reclamation plan to
consider the use of bioengineering techniques or woody debris --
along with rip rap -- as a way to protect fish habitat in the
stream. This approach would be consistent with the Juneau Coastal
Management Program policies on management of river habitat (CBJ
49.70.950(c)(7). Then-current bioengineering techniques could be
considered during reclamation since additional Title 16 Fish
Habitat permits would be required from the Alaska Department of
Fish and Game prior to implementation of the Reclamation Plan.
During mine operations, Ophir Creek will be diverted into
Ivanhoe Creek. This diversion is temporary, and Coeur does not
propose to develop fish habitat in the diversion. Upon completion
of mining and milling activities, the creek will be returned to
its natural channel which will require some reconstruction (Reclamation
Plan, page 4-4). The diversion will be regraded to match the
natural topography to promote runoff in the original drainage. As
in the prior paragraph, staff recommends that then-current
bioengineered stabilization be considered as part of the
rehabilitation design to provide the requisite stabilization
while providing natural vegetation and fish habitat.
Post-Reclamation Maintenance Requirements
Ideally, a properly designed and executed reclamation plan
will leave the mine site in a condition requiring no continuing,
long-term maintenance to achieve an enduring, high-quality
environment. In the plan, Coeur commits to post-closure
maintenance during reclamation of the site. Also, there is a
provision for a period of monitoring the effects of the
reclamation program until all requirements for release of the
financial warranty have been satisfied. Meeting the criteria for
warranty release, by definition, means that site reclamation has
been successful and no further maintenance is required. Until
warranty release occurs, Coeur will perform necessary
maintenance, and implicit in this is the commitment to return to
the site to correct any deficiencies.
Administrative Issues
A reclamation plan should form the basis for a binding
agreement -- a contractual obligation -- between the applicant
and the CBJ that results in a level of site restoration and
reclamation satisfactory to the CBJ. In fulfilling this
requirement, it is also useful to clearly identify the formal
procedures by which the scope and schedule of reclamation is
decided, the responsible parties, the source of funding, and all
other administrative matters bearing on the execution of the
reclamation program. Several of these matters are not addressed
in the plan in detail, but can be covered as conditions in CBJ's
large mine permit or are provided for in the CBJ Mining
Ordinance. While not a legal requirement under the CBJ Mining
Ordinance, CBJ also intends to work with the U.S. Forest Service,
Alaska Department of Environmental Conservation, and other
appropriate agencies to negotiate a multi-agency Memorandum of
Agreement to address coordination of procedural issues of mutual
interest with respect to Kensington mine reclamation. Procedural
issues that could be addressed in a MOA include: inspections,
annual reporting, coordinated review of reclamation plan
amendments, reclamation cost estimating and verification, annual
review of the financial warranty, non-compliance, and criteria
and procedures for release of a financial warranty.
Reclamation Costs and Financial Warranty
Estimates of the costs of performing various reclamation
activities are presented in the reclamation plan. The plan
estimates the final site reclamation cost, based on 1996
Davis-Bacon wages, in a range from a low of about $3.5 million,
after initial construction but before production, to a high of
about $4.9 million, as the mine nears the end of its design life.
At its peak, the reclamation cost is equivalent to about $18,300
per acre of disturbed ground.
These estimates include costs for reclamation monitoring of
revegetation, surface water quality, and hydrocarbon testing over
a five-year period. For planning purposes, the Reclamation Plan
generally identifies a five-year period following reclamation by
which time warranty release criteria are assumed to be met. It
should be recognized that this post-reclamation period may be
shortened or extended, depending upon the success of reclamation
activities and for specific project components. The
aforementioned release criteria of 75 percent live
self-sustaining vegetation cover and the site meeting Alaska's
Water Quality Standards will determine when reclamation goals
have been satisfied and reclamation monitoring would be
terminated. As noted previously, the cost of post-closure,
reclamation-stage maintenance work would be borne by Coeur.
The Reclamation Plan estimates do not include the costs for
permit-specific, long-term monitoring of, for example, the Dry
Tailings Facility as may be required by ADEC in the State solid
waste disposal permit. The staff report on Solid Waste notes that
ADEC has required 30-year post closure monitoring (with bonding
to cover monitoring costs) for tailings structures at the Fort
Knox and Illinois Creek mines in Interior Alaska.
In general, unit costs used in the estimate are realistic and
all major components of reclamation cost have been taken into
account. Costs reflect the payment of "Davis-Bacon"
scale wages as would be the case with governmental involvement in
reclaiming an abandoned project site. Adequate provision is made
for incidental project management and inspection, and there is a
project continency fund as well.
As part of the previously mentioned multi-agency Memorandum of
Agreement, the agencies and applicant have expressed interest in
achieving a single financial warranty to meet all reclamation
responsibilities. In the interim until such a MOA can be
negotiated, CBJ will require the applicant to establish a
financial warranty to cover reclamation costs for initial
construction. The staff report on Financial Warranty discusses
this reclamation warranty and recommends a dollar amount and
procedure for verifying cost estimates in the future at the time
of warranty renewal.
STAFF FINDINGS
(CBJ
49.15.330(e)(1)(B))
Yes. The revisions in the Reclamation Plan
(August 1997) provide sufficient information for staff
review and recommendation.
2. Will the reclamation aspect of the proposed
development endanger the public health or safety? (CBJ
49.15.330 (f)(1))
No. The Reclamation Plan (August 1997) calls
for removal of mine buildings and plugging the mine
portals as long-term measures to protect public safety.
Besides the remote location of the mine site, the permit
condition that the reclaimed mine site meet Alaska Water
Quality standards ensures that the proposed project will
not endanger public health.
3. What will be the effect of reclamation of
the project site on the value of property in the
neighboring area? Will reclamation of the project site be
in harmony with the neighboring area? (CBJ
49.15.330 (f)(2))
In general, the reclamation is likely to have a
positive effect on neighboring property as the reclaimed
mine site reverts to a more natural appearance in keeping
with the surrounding area. Revegetation test plots during
the life of the mine will help tailor mine reclamation
activities to the specific habitats found at the
Kensington mine site. A condition requiring 75 percent
live cover of self-sustaining vegetation prior to release
of a financial warranty helps ensure that the project
site will be adequately reclaimed and will be in close
harmony with the neighboring area. Also, the Modified
Landscape land use designation under the Tongass Land and
Resource Management Plan, which is applicable to the
reclaimed mine site, strives for restoration so that the
site is visually compatible with the natural
surroundings.
4. Does the city and borough approve of the
operator's reclamation plan? Does the reclamation plan
meet CBJ requirements? (CBJ 49.65.135(a)(6) and
(b))
With the conditions of the large mine permit, the Reclamation Plan (August 1997) meets CBJ requirements. Staff recommends approval.
STAFF RECOMMENDATION
In addition to recommendations in the staff reports on
Financial Warranty and Visual Resources, staff recommends that
the following conditions be included in the large mine permit:
2. The operator shall notify the department of
proposed changes in mine operations that may affect the
total amount of surface area disturbed or the reclamation
in the approved Reclamation Plan in accordance with CBJ
49.65.155. To the extent possible, such notification will
accompany the annual progress report submitted to the
department.
3. In the annual progress report to the department,
the operator shall provide data and analysis about the
results of any revegetation test plots and shall describe
how successful test results could be incorporated into
revegetation practices and amendments to the approved
Reclamation Plan. The operator shall also report and
analyze water quality monitoring data from reclaimed
sites in the annual progress report.
4. To be considered successful and prior to final
release of the financial warranty by the department, mine
reclamation shall meet the requirements of CBJ
49.65.135(b), 49.65.140(a) and other conditions of the
large mine permit. Reclaimed sites shall also support 75
percent live, self-sustaining vegetative cover where
revegetation has been undertaken, and runoff from
reclaimed sites shall meet Alaska Water Quality
Standards.
5. Reclamation of streams and the Ophir Creek
diversion channel shall include consideration of
bioengineering techniques to protect fish habitat in
addition to the placement of rip rap to meet the primary
reclamation objective of stabilization.
6. Topsoil or growth media shall be applied over regraded areas to a minimum depth of one foot, subject to modification based on the results of site-specific revegetation test plots identified in Permit Condition #3 above.
Return
to Kensington Mine Review Page
Return to the
Capital City Home Page
Our URL is http://www.juneau.lib.ak.us/cdd/Kensingt.htm