MINUTES
PLANNING COMMISSION
CITY AND BOROUGH OF JUNEAU
REGULAR MEETING
March 13, 2001
Chair Johan Dybdahl called the regular meeting of the City and Borough of Juneau Planning Commission to order at 7:00 p.m., in the Assembly Chambers of City Hall.
I. ROLL CALL
Commissioners present: Roger, Allington, Mike Bavard, Dan Bruce, Johan Dybdahl, Maria Gladziszewski, Mark Pusich, Merrill Sanford
Commissioners absent: Marshal Kendziorek, Jody Vick
A quorum was present.
Staff present: Tim McGuire, CDD Principal Planner; Oscar Graham, CDD Planning Supervisor; Terry Camery, CDD Planner
Other CBJ staff present: John Stone, CBJ Engineering; Rory Watt, Chief CIP Engineer
II. APPROVAL OF MINUTES - None
III. PUBLIC PARTICIPATION ON NON-AGENDA ITEMS - None
IV. POSSIBLE RECONSIDERATION OF THE FOLLOWING ITEM - None
V. CONSENT AGENDA
Mr. Dybdahl announced that there were three items on the Consent Agenda and he inquired if there was any public comment. No one from the public wished to comment, and there were no questions from the commissioners.
Mr. Bavard noted, for the record, that a
letter in opposition to the removal of the right of way,
SUB2001-00004.
No other objections were noted and so the items from the Consent
Agenda were approved.
SUB2001-00004
Removal of "right-of-way" status of Lot 16C, U.S. Survey 3055.
Location: POINT LENA LOOP ROAD
Applicant: CITY &
BOROUGH OF JUNEAU
SE2001-00008
A Conditional Use permit for retail sales of seafood to general public in an industrial zone.
Location: 5165 GLACIER HWY
Applicant: JOANNE SCHMIDT
Staff recommendation: It is recommended that the Planning Commission adopt the director's analysis and findings and grant the requested conditional use permit. The permit would allow the utilization of a temporary building for a retail use. The approval is subject to the following conditions:
VAR2001-00006
A variance to reduce the required minimum lot width at the front of the building from 30 feet to 27. 21 feet for proposed Lot 5B, Lake Hills Subdivision to allow the existing two-unit structure to be developed as a common wall dwelling.
Location: 3854 LEE COURT
Applicant: RICHARD HARRIS
Staff recommendation: We recommend that the Board of Adjustment adopt the director's findings and staff analysis which conclude that criteria #1-6 are met and approve the request to reduce, the minimum lot width at the front of the building from 30 feet to 27. 21 feet for proposed Lot 5B, Lake Hills Subdivision to allow the existing two-unit structure to be developed as a common wall dwelling.
VI. CONSIDERATION OF ORDINANCES AND RESOLUTIONS - None
VII. UNFINISHED BUSINESS
VAR2001-00003
A variance to allow a two story detached
garage with living space above in a 10-foot setback where 17.5
feet is required.
Location: 17090 GLACIER HWY
Applicant: LYNETTE CAMPBELL
Staff report: Ms. Camery gave a
revised staff report to the Planning Commission. The proposal was
first heard at the February 27, 2001 meeting but tabled to allow
staff the opportunity to gather additional information. Ms.
Camery reports that after obtaining further information, the
staff report has been substantially revised and CDD now
recommends approval of the requested Variance. As it was
originally presented, the proposal is a Variance to the front
setback of 17.5 feet. It is a Variance to place a two-story
garage at the 10-foot setback line, rather than the 17.5 setback
line. It is no a Variance to a one-story or square footage
requirement of the garage exception clause of the Code.
Concerns were mentioned with regard to the application of the
garage exception to this case. The applicant laid the foundation
for the garage in accordance to the building permit issued on
January 22, 2001. The building inspector allowed the foundation
to be placed at the 10-foot setback line because the permit forms
noted that the garage would meet all the garage exception
criteria, which allows the garage to be placed up to 5 feet from
the setback. The applicant had been told that the proposed garage
would meet the exception criteria if the garage were limited to
one-story. The applicant then applied for building permit, with
proposal for a one-story garage, 10 feet from the setback, as a
fall back option if the Variance to build the garage with the
second story was not approved. However, building staff had
overlooked the second part of criteria no. 3, which not only
limits the garage to one-story, but also limits it to 600 square
feet. The applicant's garage is 806 square feet and is therefore
disqualified from meeting all garage exception criteria. The
building permit was therefore, issued in error.
Staff has researched department policy and concludes that the
applicant may still meet garage exception criteria if the garage
is limited to one-story and the floor plan is altered. As
described in detail in the staff report. Staff will make a
determination at a later date if this option becomes a necessary
consideration. However, the applicant has stated that they will
pursue a two-story garage, even if it requires moving the
foundation.
A second concern raised at the February 27th meeting
was the inaccuracy of the applicant's site plan. The applicant
has since submitted an as-built survey, which is attachment D.
Staff has changed the recommendation in support of granting the
Variance by changing determination of the criteria 1, 5 and 6. As
well, the analysis of criteria 2 and 3 has also been changed.
In the original staff report, it was determined that Criteria No.
1 had not been met because the owner could have built a smaller
garage, or reduce it to one-story so that it met the garage
exception. In the revised analysis, the garage exception does not
apply and staff has considered that the purpose of the proposal
is to provide living space as well as garage space. Factoring the
second story living space of the garage, the applicant's total
living area would be 2,161 square feet. This is completely
comparable to other homes in the vicinity. In fact, without the
addition, the Campbell's home would remain one of the smallest
homes. Therefore, staff has determined that the Variance would
provide substantial relief for the property owner and it would be
consistent with justice to other property owners and Criteria No.
1 is met.
Ms. Camery has added more information to support Criteria No. 2.
Staff determined that placing the proposed garage within the
required setback would create wider separations between the home
and the garage than the proposal requiring a Variance. The wider
distance may have a greater visual impact on the single-family
character of the neighborhood. The Variance also eliminates the
need to place the structure near the drainage and cut down trees
near the drainage, which will further minimize negative impacts.
Additionally, if the two-story garage were constructed within the
required setback, it would be more visible to neighbors. Criteria
No. 2 is met.
Additional supporting information was also added to support the
determination that Criteria Nos. 3 and 4 were met.
More significantly, staff changed the analysis and determination
of Criteria No. 5 after finding that the Variance meets the
requirements of (C) that a Variance may be granted if compliance
with existing standards would be unnecessarily burdensome because
unique physical features of the property render compliance with
the standards unreasonably expensive.
Ms. Camery determined that placing the garage within the required
setback would put the structure at the edge of a slope and a
significant drainage. As well, the building pad would be within
the drainage itself. Ms. Camery reports that this feature was not
noticed at her first site visit because the area frozen and was
under several inches of snow. As such, it appeared to be minor.
Subsequent site visits revealed that the slope was obvious and
the drainage had a significant amount of flowing water. Ms.
Camery concludes that neighboring property owners face potential
expenses if the impact to the drainage changes the water flow
through their lots. She feels that adding fill to build up to the
drainage and adding a new system of culverts would be necessary
in an attempt to stay ahead of the water flow changes. Recent
letters from neighbors that were supported by Department of
Transportation officials expressed concerns over this issue and
voiced their support in granting the Variance. Based on this
additional information, Ms. Camery determined that Criteria No. 5
have been met.
In light of new evidence and analysis, particularly the
significance of the drainage issues, staff has changed the
previous determination and finds that Criterion No. 6 is also
met. This Criterion states that a Variance may be granted if a
grant of the Variance would result in more benefits than
detriments to the neighborhood. Several features in support of
this finding are that granting the Variance would lessen the
visibility to both uphill and downhill neighbors. Also, granting
the Variance would allow the structure to be built without
disturbing the drainage and changing the water flow through the
subject property and the neighboring properties. Ms. Camery finds
that granting the Variance would bring more benefits than
detriments to the neighborhood.
Conclusion
After reviewing the criterion for variances found in CBJ 49.20.250, it is evident that there are unique physical features associated with this site that create a hardship and practical difficulty to keep the applicant from complying with regulations and justify the Variance. Furthermore, placement of the garage within the proposed location appears to minimize both visual and environmental impacts to the neighborhood. These impacts would be exacerbated if the required setbacks were followed. Therefore:
Staff recommendation: That the Board of Adjustment adopt the staff analysis and director's findings and grant the requested Variance.
Public testimony;
Sheila Degener, 17050 Glacier Highway, is the neighbor to the south of the Campbell's property. Ms. Degener notes that the revised staff report and submitted letters of support focus on tree removal and drainage concerns. Her comments aimed to rebut these points. First of all, the trees that would need to be logged, if the applicant were required to move the garage do not provide any screening whatsoever. She states that the trees are barely visible from her property and to the properties of her neighbors. Ms. Degener also comments on the problems of drainage. Development and poor drainage management has led to problems to the city's roadways and down hill landowners. The applicant and CDD staff maintains that moving the structure would force the altering of an existing drainage and the removal of trees. She is unmoved by this argument, stating instead that the applicant has already altered the drainage, illegally, without a permit, a properly engineered plan and without an inspection. The applicant's building preparations have already caused damage to their property, Ms. Degener asserts. She states that their situation might be improved upon if the drainage were altered. This would afford the applicant the opportunity to correct an existing problem with the benefit of an engineered plan and proper inspections. Ms. Degener feels that granting the Variance would not preserve the aesthetics of the neighborhood with regard to trees, and drainage issues that already exist would continue.
George Campbell, 17090 Glacier
Highway, is the applicant and he appears to clarify points in
dispute and to answer any questions. First, he responded to
claims that they carried out unpermitted work to the drainage.
Mr. Campbell states that he received a grading permit for the
site preparation carried out two years ago. The drainage was
relocated approximately 15 feet to the side of where the garage
will go. The drainage is directed through the root system of a
large spruce tree. As he worked on the pad, that drainage became
an issue when it was noted that it fans into about 25 different
directions. Workers attempted to channel the fanning more into
the stream to protect the neighbor's property. He had discussed
this with the neighbors and heard no objections at the time.
Mr. Campbell responded to the assertion that a build up of silt
on the Degener's property is caused by the Campbell's. Silting
occurs not because the streambed had been moved, but because it
naturally occurs in that area. Mr. Campbell dug a four-foot deep
pond and within two months it had been nearly filled in with
sediment. If the foundation needs to be moved, trees and their
root systems must be removed. The detriment of that action is
that root systems keep the soils and streambeds in place.
He said one complicating factor that has increased the water
table in the area has been the conversion to city water system.
This had a huge impact on the volume of water that stays in the
stream. The problems are so extreme that some of their neighbors
are in daily contact with CBJ Engineering as they try to resolve
their drainage problems.
In conclusion, the work to the stream was completed with permits
and the flow change has not created a disturbance to the area.
The drainage problems arise from the natural setting of their
properties.
Mr. Allington wondered if the alteration to the stream increased
the length of the run through Mr. Campbell's property. Mr.
Campbell thought that it increased it a little. The original
stream traveled straight down, through the center of his property
and now it bows to the side of his house.
Alan Degener, 17050 Glacier Highway,
noted that he testified and submitted written testimony at the
last public hearing and he wished for his testimony in opposition
to stand. Mr. Degener has a copy of the permit issued two years
ago. The project description states that "place a two foot
cap for a driveway to parking pad." It doesn't mention
drainage issues, however, the application indicated that a
grading plan stapled to it, but it wasn't attached to his copy.
Regardless of what may have been permitted, the completed project
did not receive an inspection.
Mr. Degener emphasized that the heart of their concern is the
fact that a two-story structure imposing itself onto the
Degener's private back yard. It would be detrimental to their
privacy, increase light levels, and it would be extremely
difficult to screen given its relative height to their back yard.
He worries that the structure could lead to an oversized,
unattached apartment. Rentals can be hard to detect.
Mr. Degener opposes the staff's recommendation and he is
surprised by the reversal of their opinion. He thinks that this
has put the Planning Commission into a difficult position and he
can see only two solutions. First, grant the Variance and allow
the structure to be built where it is; or secondly, move the
structure to a different location. To assist the applicant in
finding a win-win solution, Mr. Degener presented some
alternative building design ideas to the applicant. The applicant
said they had considered the ideas but had not liked them. Mr.
Degener emphasized that there are alternatives to be explored
that can also meet everyone's goals.
From his point of view, the applicant has made several mistakes.
One, he did not consult with the neighbors with regard to their
plans. Once they became aware that the neighbors had a right to
comment in the public process, they acted. However, by then the
applicant had poured the foundation. He laments that a better
solution could have been achieved. The second mistake made by the
applicant was waiting for the Variance process to be over before
laying the foundation. If the Planning Commission approves the
Variance, the people who will pay for that mistake will be the
neighbors. He hoped that they would oppose the Variance.
Mr. Sanford asked what the distance between Mr. Degener's house
and the applicant's was? Mr. Degener estimated the distance to be
over 60 feet. He said the distance was not an issue, the height
was. The Campbell's property is 15 feet higher than the Degener's
and then the proposed height of the garage was an additional 30
feet up. He anticipates the garage to tower 45 feet above the
back yard.
Mr. Pusich asked for clarification on the loss of privacy. Mr.
Degener said that view from the garage would peer down into his
bedroom windows. Also, the Degener's have a hot tub in their back
yard. The wall of the structure that will face the Degener home
is primarily glass and the height will prevent any screening.
Ms. Gladziszewski asked staff to clarify that if the Variance
were not granted, the applicant could move the foundation 7 feet
and build their two-story garage? Ms. Camery said that was
correct.
Mr. Bavard asked what tree cutting issues had been problematic.
To Ms. Camery's knowledge, the applicant had not removed any
trees to accommodate the placement of the pad. Should the
applicant move the pad to comply with the required setbacks, tree
removal would then occur.
Mr. Bavard also asked about the grading permit and assertions of
unauthorized filling. Phil Zenter from CBJ Engineering visited
the property to evaluate the grading referred to by the Degeners.
He determined that no illegal filling had been done. The
applicant had permits for all existing work.
Planning Commission Action:
Motion: by Mr. Bruce for acceptance of VAR2001-00003, as revised and accept the findings and recommendations of staff.
Mr. Bruce said the he appreciated the
concerns of the Degener's but he thought the applicant was
certainly within his rights to seek the Variance, considering the
terrain and topography that he's contending with.
Mr. Bavard also supports the motion. He didnt think that it
was an unreasonable use of the property and he was convinced that
trying to move things around to meet setback requirements would
create problems.
Mr. Allington noted that Dean Griggs is a hydrologist at the
Department of Transportation who is well qualified to comment on
the site.
Ms. Gladziszewski said that if the Variance is not granted, the
applicant could still build a two-story garage without further
comment from the Planning Commission. She was also convinced by
the letters from engineers and supports the motion.
Mr. Pusich said he finds staff's analysis and findings very
difficult to argue with and he supports the motion. If the
Variance is not granted, the impacts cited by the Degeners will
still occur. The only difference is that the environment will be
harmed.
Roll Call Vote:
Yeas: Allington, Bavard, Bruce, Dybdahl,
Gladziszewski, Pusich, Sanford
Nays:
Absent: Kendziorek, Vick
VIII. REGULAR AGENDA
Mr. Dybdahl announced that CSP2001-00003 and USE2001-00009 would be heard together as one item.
CSP2001-00003
A city project review for a building of approximately 27,000 square feet for use in winter as an indoor ice rink and in summer as a multi-purpose facility at Savikko Park.
Location: 121 DOCK ST
Applicant: CITY & BOROUGH OF JUNEAU
Staff recommendation: That the Planning Commission adopt the director's analysis and findings and approve the city project review as identified above. The approval would allow the development of the Treadwell Arena, a building of approximately 27,000 square feet for use in winter as an indoor ice rink and in summer as a multi-purpose facility for tennis, basketball, in-line skating and special events. The approval is subject to the following condition:
USE2001-00009
A Conditional Use permit for a building of approximately 27,000 square feet for use in winter as an indoor ice rink and in summer as a multi-purpose facility at Savikko Park.
Location: 121 DOCK ST
Applicant: CITY & BOROUGH OF JUNEAU
Staff recommendation: That the Planning Commission adopt the director's analysis and findings and grant the requested Conditional Use permit as identified above. The approval would allow the development of the Treadwell Arena, a building of approximately 27,000 square feet for use in winter as an indoor ice rink and in summer as a multi-purpose facility for tennis, basketball, in-line skating and special events. The approval is subject to the following condition:
Staff report: Oscar
Graham would brief the Planning Commission on the staff report
prepared by Gary Gillette. Mr. Gillette was out of town. The
project involves the construction of a 27,000 square foot ice
rink structure is intended to be reminiscent of historical
Treadwell buildings. Staff hopes that the incorporation of
historical features be reinforced into the design of the
building. Mr. Graham suggests simply adding window simulations or
refinement of the roofline. The design team is amenable and
later, John Stone of the Public Works Department will discuss
that issue.
There were no significant traffic impacts, due to the excellent
location of the facility and the adjacent road system. The
parking requirement was calculated to be 1 space per 4 users, or
a maximum parking requirement of 85 spaces. Currently, there are
190 parking spaces available and staff determined the parking to
be sufficient.
The proposed building location is in an established park. Savikko
Park has been pinpointed to be the site of the ice rink and it is
therefore compatible with neighborhood harmony.
The project is being constructed with a combination of public and
private sources; however, full funding is not currently in place.
The intent is for the project to be constructed in phases, as
funding allows. Phase I involves the completion of the building
shell itself. The facility will be owned and maintained by the
CBJ and operated by a nonprofit organization.
The CDD staff recommends that the Conditional Use permit subject
to one Condition requiring that a lighting plan be submitted
prior to issuance of the building permit. Staff also recommends
approval of the City Sponsored Project subject to one
recommendation, which encourages the Assembly to authorize design
changes to the building that would incorporate historic features
in the buildings design. Mr. Graham said that the design
team would address the technical questions, relative to the
project. He introduced John Stone, from the Public Works
Department
John Stone, Director of the CBJ
Engineering Department and Chair of the Ice Rink Working Group
that the Mayor convened in November 2000. The working group put
together a conceptual design and cost estimate of the Treadwell
Arena and they are now working on the operations and revenue side
of the project. The information will be presented to the
Assemblys Public Works and Facilities Committee on April 4th.
From there, the project will be forwarded to the Assemblys
Finance Committee with the outlook that people will be on the ice
in a year.
Mr. Pusich said that one recommendation under review involved
design changes to the building. Has the Working Group discussed
the changes with staff and are they comfortable with that? Mr.
Stone said it had been discussed and the Working Group plans to
meet with Gary Gillette to see what he had in mind. The main
concern seems to be breaking up the monotony of the walls. While
the design team was amenable to the suggestion, he cautioned that
the projects budget is a significant limitation. One
thought is to list Mr. Gillettes suggestions as
"alternates" in the bid package and to see how much it
costs. If the project budget supports it, fine.
Mr. Bavard noted that the construction of the Treadwell Arena
meant the displacement of the current basketball courts. What
types of consideration would be given to accommodating the
multiple uses of Savikko Park within the Arena? Would there be a
fee for the summertime use? Mr. Stone said the flooring has not
yet been specified, however, a suggestion is a brushed concrete
surface that allows for alternate uses such as basketball and
inline skating. The Working Group hasnt addressed whether
or not there would be a fee for summertime use of the facility.
Mr. Bruce asked how old the surface that is currently in place
is? Mr. Stone said that the basketball court surface was 25 years
old.
Mr. Sanford asked what changes would be made to the walking path?
Mr. Stone described that the building would be pushed up against
the hillside, to the extent possible. The path would be moved to
the front of the structure.
Mr. Sanford asked if any softball field space would be lost in
order to accommodate the new facility. Mr. Stone indicated that
no fields would be lost.
Mr. Allington asked if he would have a problem if the
recommendation or suggestion to incorporate historical qualities
to the design of the building to a requirement?
Mr. Stone said that he couldnt commit the Assemblys
money before hes had a chance to talk to them. The design
team would meet with Mr. Gillette to hear what the concerns are
and then they would take the recommendation to the Assembly.
Ms. Gladziszewski asked if the Working Group had bids for the
building as it's currently designed? Mr. Stone said that the bids
were in and the total project is approximately $3 million
dollars. The building alone is $350-400,000. It is unknown what
additional monies would be required to make the changes Mr.
Gillette had in mind.
Mr. Pusich asked if the facility would ever be used in the
summertime for ice-skating. Mr. Stone said a final decision
hasnt been made yet. He noted that it must be determined
prior to construction. As it stands, seven months per year the
facility would sport ice, the remainder would be dedicated to
other uses.
Mr. Sanford asked if the proposal had been presented to the
Douglas Advisory Board? Mr. Sanford said that March 21, the
Working Group is set to meet with the Douglas Advisory Board. He
also believed that the idea has been presented to them in the
past.
Emily Wall, 513 5th Street, Douglas, came to the meeting prepared to recommend that the Conditional Use permit be continued; however, most of her questions have now been addressed. Ms. Wall supports Mr. Allington's idea that the design recommendations are converted into requirements. She hopes that something can be done so that there isn't a huge metal shed sitting in the middle of Savikko Park. Other building materials such as wood could be incorporated into the design. She understood the constraints that design teams typically operate within, and she commended those involved for their hard work. However, she supported postponing the construction till the next year so that more funds could be raised and a better-looking building would result.
Sandy Williams, 640 5th Street, Douglas: lives in the vicinity of Savikko Park and he also serves on the Working Group. He agrees that the ice rink facility will look like a large metal-sided building, and unless aesthetic changes are made, it won't look pretty. However, it reminds him of what the City built 25 years ago: the Parks and Recreation Departments Maintenance Facility. As such, Mr. Williams thinks that the ice rink will blend in with its environment. Because of the ice rinks proximity to the baseball fields, no windows will be considered. False window frames to enhance the appearance are low budget options that may be possible. Other changes, such as lifting it up or lowering it would be cost prohibitive. Mr. Williams notes that the completed structure is estimated to cost $3.1 million dollars and the group has $2.1 million dollars will put ice into the facility. The primary objective is to get the ice in the building and other enhancements can be added later.
Chair Dybdahl closed public testimony.
Planning Commission action:
Motion: by Mr. Bruce, that the Planning Commission grant USE2001-00009 adopting staff's analysis, findings and recommendations. As well, that CSP2001-00003 is adopted.
Mr. Bruce recalled an election in 1990
where the public stated strongly that they didn't want to spend
the amount of money that the CBJ envisioned for an ice rink
building. From his experience sitting on the Public Works
Committee, he understands the efforts involved to keep the
project as economical as possible. Extras would be great, but the
public doesn't support a lot of aesthetics, they want a cheap
building. Furthermore, Mr. Bruce didn't support adding any
aesthetic requirements because that could be the death knell of
the project. Mr. Bruce recounted that all of the ice rinks he has
known and loved have all looked like the big metal shed that is
the Treadwell Arena.
Mr. Pusich also supports the motion. The public need has been
clearly identified and he thinks the Working Group can work out
the suggested design changes to the building.
Mr. Allington suggested a minor modification to Recommendation
No. 1, specifically stating that exterior lighting will be
"full-cutoff luminaires." The public is fickle, today
they want the ice rink but tomorrow they'll complain about the
looks of the building, stating that it wouldn't have been
approved if it were a private project. Nevertheless, he supports
the motion.
Ms. Gladziszewski said she supports the motion, but she would
hate to see a large metal building in Savikko Park. Its an
issue of how much does it cost, and what is affordable. The
question is for the Assembly to answer. She would also prefer
deferring construction so that the building was more
aesthetically pleasing and not a big tin shack.
Roll call vote
Yeas: Allington, Bavard, Bruce, Dybdahl,
Gladziszewski, Pusich, Sanford
Nays:
Absent: Kendziorek, Vick
CSP2001-00004
A Review of a City Project to reconstruct Gastineau Avenue from 2nd Street to Ewing Way including water, sewer, storm drain, sidewalks, retaining walls, and stairways.
Location: GASTINEAU AVENUE
Applicant: CITY & BOROUGH OF JUNEAU
Staff report: Tim McGuire, CDD Principal Planner introduced the proposed project to the Planning. The reconstruction of Gastineau Avenue has been in the works for quite some time and it has undergone extensive reviews with ample involvement from the public. Mr. McGuire announced that Nathan Leigh from the Engineering Firm, USKH will present the project description and the project manager, and Joe Costello from CBJ's Engineering Department will be available to answer questions.
Nathan Leigh, of USKH Engineering reported that the reconstruction project was initiated by public meetings that resulted in over 275 comments detailed what was important to the residents of Gastineau Avenue. Several design options were explored with prices ranging from 7million to 5.5 million dollars. The least expensive option covered the most important priorities including the replacement of the retaining walls and water lines, separating the water and sewer lines and upgrading the stairs and utilities and replacement of existing features. Planners went back to the public to develop an alternative and to identify what was most important to them. They were told that the removal of the chain link fence, increase sidewalks and to rebuild the road. Lesser priorities included road widening. The final design alternative was finally selected and it includes the following:
Additional funding sources were sought as
the currently projected cost for the project remains at 5.4
million dollars.
Mr. Dybdahl asked if Gastineau Avenue was the only remaining
neighborhood where the water and sewer were combined? Rory Watt,
CBJ's Chief CIP Engineer came forward to respond. He stated that
with each street reconstruction projects, the stormwater and
sewer lines have been separated. There are some remaining areas
in the downtown and Highlands area where the systems are
combined. The problem with combined systems is that during a
storm, there are combined sewer overflows into the Gastineau
Channel. Years ago, there were about a hundred of these events in
a year. Today the overflows happen only once or twice a year.
Mr. Allington was concerned about access to the neighborhood. How
would people access their homes with groceries and other loads?
Is there any way to provide access by carrying out the project in
stages?
Mr. Watt said that construction on the project would be difficult
and will result in the road being closed. The contractor will
keep pedestrian access open all the time but they will not be
able to drive most of the time. The contractor will be allowed to
close the road from 8 a.m. to 5 p.m. during construction of the
utilities. During construction of the retaining wall, the road
will be closed for three weeks at a time, Monday through Friday.
The public is fully aware that the road reconstruction will
prevent vehicular access to Gastineau Avenue for the bulk of the
summer construction season.
Mr. Sanford asked if the Gastineau Avenue was on a looped system?
Mr. Leigh said that it was. There was a water line connection at
Ewing Way and South Franklin as well as Gold Street and Second
Avenue.
Mr. Sanford asked for a description of the temporary fire access
route. Mr. Leigh said that the existing access route from the
gold mine to Thane would be utilized. This will require
constructing about 300 feet of road between Thane and the mill
site. The contractor will also utilize the road for construction,
however it will not be open to the public.
Mr. Pusich asked if service providers such as oil delivery
vehicles had been informed of the limited hours and days of
access to Gastineau Avenue? Mr. Leigh said that the contractor
would coordinate all of these issues.
Mr. Bavard asked when the bids would be received? Mr. Leigh
expected to be reviewing bids in four weeks.
Staff recommendation: That the Planning Commission adopt the director's analysis and findings and approve the City Project Review to reconstruct Gastineau Avenue from 2nd Street to Ewing Way including water, sewer, storm drain, sidewalks, retaining walls, and stairways. The approval is subject to the following condition:
Mr. Allington asked if there was need for a Condition that required advance notice is provided to the residents. Mr. Leigh indicated that the residents would be updated on road closures weekly.
Public testimony:
Nancy Waterman, 227 Gastineau Avenue, complimented staff on how well they have worked with the neighborhood. She thought that one thing which had been looked at years ago was putting in underground utilities. While that is not feasible due to the expense, Ms. Waterman hoped to continue discussions with Mr. Watt with regard to installing conduits for cable and lateral wires. The stability of the hillside during the construction phase was also a concern to Ms. Waterman. In that regard, she was pleased with staff and how they've worked out solutions to her satisfaction.
Robert Steike, was a property manager for the state apartments located at the end of Gastineau Avenue. Mr. Steike spoke in support of paving Gastineau Avenue to the end. He thought that if the road looks like a city street then it will be treated like a city street and he would like to see an end to the excessive littering that currently takes place in the vicinity of his home. Other benefits of a paved road include diminished dust and less likelihood that people would hide out.
Robert Clark, is a neighbor to
Robert Steike and he spoke in support of a complete paved road.
He also raised the issue of an old retaining wall. Mr. Clark
recalled CBJ staff telling him that after to road is rebuilt,
maybe they would have time and money to work on the old retaining
wall. He understands that the retaining wall that keeps the road
off of his building will not be reconstructed.
Mr. Bruce commented that the Public Works Committee held a
hearing dealing with whether or not Gastineau Avenue should be
paved from the green house to past the bridge. The meeting
concluded with CBJ staff planning to poll the affected residents
of Gastineau Avenue to determine what their wishes were.
Cami Clark, also lives at the end of
Gastineau Avenue. She stated that it would be a shame for so much
money to be spent on the project without paving Gastineau Avenue
completely. She was also disappointed by the fact that the
reconstruction of the retaining wall next to her home was not
included in the project. Each year, the old retaining wall is
pushed up against her home and they must push it back off
repeatedly. Ms. Clark states that the CBJ had always told them
that the retaining wall would be addressed with the
reconstruction project. She is shocked that this years
property tax assessment spiked in price yet the CBJ had no plans
to fix the retaining wall.
Mr. Bavard asked about the closure of the streets and what hours
of operation would the City limit the contractor to? In the past,
the City has tried to encourage expedited completion of projects
by encouraging long working days six days out of the week. In
this situation, the contractor must make special accommodations
for the residents accessibility.
Mr. Leigh said the contractor could work longer than 8 to 5 p.m.,
but the contractor cannot keep the road closed longer than that
time frame. Each competing need was balanced.
Mr. Watt clarified that the project includes three major
retaining walls. When work on the retaining walls is under way,
the street would be closed to traffic from Monday morning to
Friday evening. The street would be reopened for weeks in a row.
The work schedule is actually quite aggressive.
Ms. Gladziszewski asked for an explanation of the Clarks
retaining wall and the paving of Gastineau Avenue from the green
house.
Mr. Watt explained that currently at approximately Bulger Way (a
5-foot alley way), and between Mr. Keenes property, there
is an old bridge structure. The paving ends there. Originally,
staff proposed that paving continue to the end of the road. Some
residents opposed the paving because they liked the character of
the dirt road. The CBJ proposed to leave it as a gravel road,
unless there was a demonstration of support by the majority of
the affected Gastineau Avenue residents. Now it is a neighborhood
opinion question.
Mr. Watt explained that the retaining wall is a separate issue.
The Clarks retaining wall belongs to the private property
owner and it was constructed for the benefit of the building. Mr.
Watt said he only recently learned about this issue and hes
looking into its background. As he understands it, there are
issues of soil creep. Mr. Watt said that CBJ would investigate to
see if there are things that could be done to assist the Clarks
during the reconstruction, however, there must be a benefit to
the general public as well.
Mr. Allington asked if the retaining wall was holding the road in
place or the private property in place? Mr. Allington suggested
that if the retaining wall fails and impacts the road, then it
would be in the publics best interest to protect the road.
Mr. Watt stated that the wall was below the road, and he believed
it was holding the property in place.
Mr. Allington asked what the contract time limit of the project
would be? Mr. Leigh stated that its expected to be a two
construction season project, or to the end of 2002.
Mr. Allington wanted to be certain that the project
specifications required the contractor to put the road back into
passable condition at the end of this years construction
season. Mr. Leigh said that when winter comes, the contractor
would have Gastineau Avenue passable.
Mr. Pusich asked about the incentive duration stipulated in the
contract. If the contractor fails to achieve the incentive goals,
are there damages? Mr. Leigh stated that the construction is
broken into five phases. The contractor will receive a bonus of
approximately $10,000 per phase if they are completed on time. If
the contractor completes the first four phases, most of the work
will be done this season with only a small amount left over for
next year. The only provision for liquidated damages is if the
contractor does not complete the entire project by the end of
2002.
Mr. Watt added that typically, liquidated damages are only
imposed for failure to complete on time. On this project, there
was a great desire to get the project completed on time, so CBJ
is experimenting with incentive payments of about 1 ½ percent of
the final project cost.
Mr. Sanford asked how Gastineau Avenue would end following the
completion of the project. Mr. Leigh said that the road would
look the same, except it would be paved, if the majority of the
residents desire. . The alternative access road will be
obliterated by a trench and placement of boulders.
Mr. Sanford thought that it was important for safety that the
road be paved now.
Mr. Bruce reported that in the Public Works Committee, a motion
to approve the project, including the paving, was withdrawn
following a 2 to 2 vote. After that action, staff was directed to
ascertain the preference of the residents of Gastineau Avenue
that are affected.
Mr. Allington agreed with Mr. Sanford in principal, but
acknowledged that since it was the end of a road that impacted
very few residents, their preference should be respected.
Motion by: Mr. Bruce that the Planning
Commission forward CSP2001-00004 to the Assembly with a
recommendation to adopt staffs findings, analysis and
recommendations.
Mr. Bavard spoke in support of the motion. He commended staff on
their collaborative work with the residents so that the best plan
could be developed.
Mr. Bruce said that his participation on the Public Works
Committee resulted in a lot of exposure on this issue. Its
been a lot of work but he believes the final result is a great
product is something that staff can be proud of.
Ms. Gladziszewski commented on how refreshing it is to hear
citizens say thank you to the City for working with them. She
also thanked staff for their work.
Mr. Pusich noted that the residents of Gastineau Avenue have
always been a very concerned group of citizens. He was gratified
to see their needs and interests taken to heart and he is
confident that everyone will be pleased with the final results of
the project.
Roll Call Vote:
Yeas: Allington, Bavard, Bruce, Dybdahl,
Gladziszewski, Pusich, Sanford
Nays:
Absent: Kendziorek, Vick
XII. PLANNING COMMISSION COMMENTS AND QUESTIONS
Mr. Allington reminded Commissioners of his
concerns regarding the narrow road width planned for with the
Marine Park reconstruction project. He was concerned by limited
access for emergency vehicles and potential exposure to a tort
claim if an emergency vehicle is held up because of the
narrowness of the roadway. Mr. Allington checked with Rory Watt
tonight and learned that the CBJ opted not to widen the road way
because if we want 18-foot roadways then a policy must be
established. Mr. Allington suggested that staff address this
issue.
Mr. Bavard said he was interested in updates on several items
that the Planning Commission had been involved with. First, what
was the status of the Rock Dump gold mine? Mr. Bavard recalled
that when the applicant was before the Planning Commission, they
had expressed urgency. Is there any activity at the Rock Dump?
Mr. Gillette hadnt heard anything but he would check on it.
Mr. Bavard also asked about the Bicknell asphalt issue and the
Malick issue. Mr. Gillette said that the applicant was
considering going back to the original permitted site off of
Industrial Boulevard. He still has the opportunity to start
operations in the spring for several days and there is an appeal
before the Assembly also. With regard to the Malick appeal, Mr.
Gillette indicated that the permit will be remanded to the
Commission but he didnt have news on the timing.
Mr. Bavard asked what could the Planning Commission expect at the
upcoming special meeting dealing with the Totem Creek Golf
course. Mr. Graham didnt know if the applicant would
present any new information to the Planning Commission. Following
the last public hearing, the Planning Commission had requested
additional information. Excepting the Hillside Endorsement, no
new information had been submitted to the CDD.
Mr. Bavard hoped to have the entire package but he noted that
four issues remain unresolved.
Mr. Dybdahl thought that the proponents expect to have a decision
from the Planning Commission on March 20th.
Mr. Bruce noted that perhaps the applicant believes there are
issues that wont be resolved between staff and the
applicant and they are turning to the Planning Commission for a
decision.
XII. ADJOURNMENT
Motion: by Mr. Pusich to adjourn.
There being no other business and no objection Chair Dybdahl adjourned the meeting at 9:00 p.m.